{"ID":6537403,"CreatedAt":"2026-07-14T02:54:43.516908796Z","UpdatedAt":"2026-07-15T03:28:55.185153975Z","DeletedAt":null,"paper_url":"https://arxiv.org/abs/2607.11725","arxiv_id":"2607.11725","title":"Time-Lag-Aware Deep Reinforcement Learning for Flexible Job-Shop Scheduling in PPVC Module Factories","abstract":"Prefabricated prefinished volumetric construction moves most building work into module factories, whose production floor operates as a flexible job shop. A major complication is decisive: long post-operation time-lags caused by concrete curing, watertightness ponding tests, and paint drying, during which a module is blocked while its workstation stays free. On benchmark instances grounded in an official national prefabrication guidebook, these lags inflate even the optimal reference makespan by about 67% on average, and ignoring them at decision time, then repairing to feasibility, is worse than every dispatching rule. We adapt a state-of-the-art dual-attention deep reinforcement learning solver through three minimally invasive, individually ablatable extensions: lag-aware dynamics with an admissible reward bound, two anticipatory lag feature channels, and liveness-masked operation- and station-type embeddings. With every extension disabled the implementation reproduces the original solver exactly, so all gains are attributable to the adaptations. We release a public, guidebook-grounded benchmark generator. On held-out instances the learned policy is the strongest solver-free scheduler: it reaches within about 4% of a constraint-programming reference and beats every dispatching rule and a genetic-algorithm metaheuristic, with its advantage widening under capacity contention, and a single size-mixed policy carries this lead across the trained range of factory sizes. It needs no solver, model, or license in the loop and re-plans within seconds of a disruption; where an exact solver can be deployed, that solver remains the quality ceiling, a boundary we map explicitly.","short_abstract":"Prefabricated prefinished volumetric construction moves most building work into module factories, whose production floor operates as a flexible job shop. A major complication is decisive: long post-operation time-lags caused by concrete curing, watertightness ponding tests, and paint drying, during which a module is bl...","url_abs":"https://arxiv.org/abs/2607.11725","url_pdf":"https://arxiv.org/pdf/2607.11725v1","authors":"[\"Ziheng Zhang\",\"Wei Zhang\"]","published":"2026-07-13T15:50:00Z","proceeding":"cs.LG","tasks":"[\"cs.LG\",\"cs.AI\",\"math.OC\"]","methods":"[\"Reinforcement Learning\"]","has_code":false}